NCAS
OSC FY 02/03 NCAS JANUARY MONTHLY OPERATIONS
CALENDAR FOR PERIOD 07, ENDING 01/31/03
ACTIVITY SYSTEM DATE COMMENTS
New Year's Day Holiday ALL 01/01/2003 System down for New Year's Holiday
Close prior period GL 01/02/2003 December 2002 is closed
Pre-Month End Reports GL 01/02/2003 Pre-month end reports available in X/PTR.
Health Benefits Interface FC 01/02/2003 Health Benefits interface posts first working day of the month.
IT Project Reports GL 01/02/2003 IT project reports in XPTR
NO PRODUCTION CYCLE ALL 01/03/2003 NO PRODUCTION CYCLE UPDATE
Inventory Recalculation IN 01/04/2003 Inventory recalculation first Saturday of each month
Saturday Hours ALL 01/04/2003 Production regions up for processing from 9am to 2 pm. No NCAS Help Desk support available.
Payroll Interface FC 01/07/2003 Run Payroll Interface - Cancellation / Rewrite - (Payroll Interface Effective Date = 12/31/02)
IT Project Reports GL 01/09/2003 IT project reports in XPTR
NO PRODUCTION CYCLE ALL 01/10/2003 NO PRODUCTION CYCLE UPDATE
1099 Changes AP 01/13/2003 Last day to make corrections to 1099 data before 2002 forms are printed
Payroll Interface FC 01/13/2003 Run Payroll Interface - Mid-Month
Check Reconciliation AP 01/13/2003 Check Reconciliation tape is posted tonight
Certified Reports ALL 01/14/2003 Certified reports for December run tonight (9th working day)
1099 Forms Printed ALL 01/15/2003 2002 1099 forms are printed
1099 Corrections and Updates AP 1/15/03-3/21/03 Agency produces manual 1099 corrections and updates NCAS for IRS electronic filing
IT Project Reports GL 01/16/2003 IT project reports in XPTR
NO PRODUCTION CYCLE ALL 01/17/2003 NO PRODUCTION CYCLE UPDATE
Inventory Recalculation IN 01/18/2003 Inventory recalculation third Saturday of each month
Holiday ALL 01/20/2003 System down for Martin Luther King, Jr. Holiday
Payroll Interface FC 01/21/2003 Run Payroll Interface - Cancellation / Rewrite
1099 Forms Pickup ALL 1/21/03 1/31/03 Agencies will be notified when 1099 forms are available for pickup from OSC
1099 Forms Review AP 1/21/03 - 1/31/03 Agency reviews 1099 forms
Current Month End Reports GL 01/23/2003 Current month end reports (MOCUR) available in XPTR; Pre-month end reports (MOPRE) discontinued
IT Project Reports GL 01/23/2003 IT project reports in XPTR
NO PRODUCTION CYCLE ALL 01/24/2003 NO PRODUCTION CYCLE UPDATE
Saturday Hours ALL 01/25/2003 Production regions up for processing from 9am to 2 pm. No NCAS Help Desk support available.
Payroll Interface FC 01/29/2003 Run Payroll Interface - Monthly
IT Project Reports GL 01/30/2003 IT project reports in XPTR
Non-System Checks AP 01/30/2003 Process Non-System check deletes and cancels
Balancing to Available Funds Report BC 01/30/2003 Run Balancing to Available Funds (BC950) report in XPTR
Automated closing of PO's PS 01/30/2003 Automated closing of applicable PO's to receiving and subsequent processing by P&C
Fixed Assets Monthly Update FA 01/30/2003 Fixed asset monthly update process includes depreciation
Open next period GL 01/30/2003 February 2003 is opened
NO PRODUCTION CYCLE ALL 01/31/2003 NO PRODUCTION CYCLE UPDATE
1099 Forms Mailed AP 01/31/2003 Deadline for mailing 1099 forms to vendors.