OSC FY 2003- 2004 NCAS NOVEMBER MONTHLY OPERATIONS
CALENDAR FOR PERIOD 05, ENDING 11/30/2003
Note:  Please see the Emergency Special Hours Request procedures if you need to request additional production cycles
ACTIVITY SYSTEM DATE COMMENTS
Escheat Notification AP 11/1 Escheat checks due to State Treasurer's Office by 11/1/03. Due Diligence letters should have already been mailed. Click on the following link for escheat procedures from the State Treasurer's Office: http://ncdst-webt.treasurer.state.nc.us/ASD/frescheat.htm
Saturday Hours  ALL 11/1 Production regions up for keying transactions from 9 a.m. to 2 p.m. No Production Cycle.  No NCAS Help Desk support available.
Inventory Recalculation IN 11/1 Inventory recalculation first Saturday of every month.
Close prior period GL 11/3 October (Period 04) is closed.
Health Benefits Interface FC 11/3 Run monthly Health Benefits Interface.
Pre-Month End Reports GL 11/4 Pre-month end reports available in X/PTR.
Payroll Interface FC 11/5 Run Payroll Interface - Cancellation / Rewrite
IT Project Reports GL 11/7 IT Project Reports in XPTR
NO PRODUCTION CYCLE   ALL 11/7 NO FRIDAY PRODUCTION CYCLE
Payroll Interface FC 11/10 Run Payroll Interface - Mid-Month.
HOLIDAY ALL 11/11 PRODUCTION REGIONS DOWN FOR THE HOLIDAY
Check Reconciliation AP 11/12 Check Reconciliation tape is posted during production run.
IT Project Reports GL 11/14 IT Project Reports in XPTR
Certified Reports GL 11/14 Month end reports must be pre-certified by this date.
PRODUCTION CYCLE UPDATE
ALL 11/14 There will be a Friday night Production cycle update.
Inventory Recalculation IN 11/15 Inventory recalculation third Saturday of every month.
Payroll Interface FC 11/18 Run Payroll Interface - Cancellation / Rewrite
IT Project Reports GL 11/21 IT Project Reports in XPTR
NO PRODUCTION CYCLE ALL 11/21 NO FRIDAY PRODUCTION CYCLE UPDATE
Saturday Hours ALL 11/22 Production regions up for keying transactions from 9 a.m. to 2 p.m. No Production Cycle.  No NCAS Help Desk support available.
Payroll Interface FC 11/24
Run Payroll Interface - Monthly.
Current Month End Reports  GL 11/26 Current month end reports (MOCUR) available in XPTR; Pre-month end reports (MOPRE) discontinued
Non-System Checks AP 11/26 Process non-system check deletes and cancellations. 
Fixed Assets Monthly Update FA 11/26 Fixed Asset monthly update process for November, includes depreciation.
Balancing to Available Funds Report BC 11/26 Run the Balancing to Available Funds (BC950) report in XPTR.
Automated closing of PO's PS 11/26 Automated closing of applicable PO's to receiving and subsequent processing by P&C.
Open next period GL 11/26 December (Period 06) is opened.
Holiday ALL 11/27
11/28
11/29
Production regions down for the holiday