| OSC FY 2002 - 2003 NCAS AUGUST MONTHLY OPERATIONS | |||
| CALENDAR FOR PERIOD 02, ENDING 08/31/2002 | |||
| ACTIVITY | SYSTEM | DATE | COMMENTS |
| Close prior period | GL | 8/1 | July (Period 01) is closed. |
| Pre-Month End Reports | GL | 8/1 | Pre-month end reports (MOPRE) available in X/PTR. Current month end reports (MOCUR) discontinued |
| Health Benefits Interface | FC | 8/1 | Run monthly Health Benefits interface. |
| Adobe reports for CAFR 11A, 30, 57 are sent to agencies and Central Managers | DSS | 8/1 - 8/31 | These reports are updated nightly. |
| Review flagged accrual reports for completeness and correctness | AP | 8/1 - 8/2 | All flagged accruals for the month of July should be reviewed for accuracy and completeness. |
| Post Flagged AP Accruals | AP | 8/1 - 8/9 | Agencies must request the posting of these accruals. Only one processing can occur for all flagged accruals for an agency. |
| Post Items Received Not Invoiced Accruals | PS | ||
| Post Flagged AR Accruals | BC | ||
| IT Project Reports | GL | 8/2 | IT project reports available in XPTR |
| NCAS Saturday Hours | ALL | 8/3 | Production regions up for keying transactions from 9 a.m. to 2 p.m. |
| Inventory Recalculation | IN | 8/3 | Inventory recalculation first Saturday of every month. |
| Payroll Interface | FC | 8/5 | Run Payroll Interface - Cancellation / Rewrite. |
| IT Project Reports | GL | 8/9 | IT project reports available in XPTR |
| Fixed Asset Deadline | FA | 8/9 | Last day to enter asset data for fiscal year ended June 30. Year ending reports are available in X/PTR under: OSCOP* FAFIN-1 YEAR END REPORTS OSCOP* FAFIN-2 YEAR END REPORTS OSCOP* FAFIN-3 YEAR END DEPR RPT |
| Check Reconciliation | AP | 8/09 | Check Reconciliation tape is posted during production run. |
| NCAS Saturday Hours | ALL | 8/10 | Production regions up for keying transactions from 9 a.m. to 2 p.m. A production cycle is being run for universities only. |
| Begin FA Processing for FY 2003 | FA | 8/12 | Enter July 2002 asset information. |
| Payroll Interface | FC | 8/12 | Run Payroll Interface - Mid-Month. |
| Certified Reports | GL | 8/13 | Certified reports for July run tonight (9th working day). |
| Fixed Assets Monthly Update | FA | 8/15 | Fixed Asset monthly update process for July, includes depreciation cycle. |
| IT Project Reports | GL | 8/16 | IT project reports available in XPTR |
| General Ledger Purge | GL | 8/16 | Purge all detail General Ledger transactions through June 29, 2001 (includes GM331 and C-Detail records). |
| NCAS Saturday Hours | ALL | 8/17 | Production regions up for keying transactions from 8 a.m. to 3 p.m. with a production cycle update. |
| Inventory Recalculation | IN | 8/17 | Inventory recalculation third Saturday of every month. |
| Payroll Interface | FC | 8/20 | Run Payroll Interface - Cancellation / Rewrite. |
| Current Month End Reports | GL | 8/22 | Current month end reports (MOCUR) available in XPTR; Pre-month end reports (MOPRE) discontinued |
| IT Project Reports | GL | 8/23 | IT project reports available in XPTR |
| NCAS Saturday Hours | ALL | 8/24 | Production regions up for keying transactions from 8 a.m. to 3 p.m. with a production cycle update. |
| Payroll Interface | FC | 8/28 | Run Payroll Interface - Monthly. |
| IT Project Reports | GL | 8/30 | IT project reports available in XPTR |
| Non-System Checks | AP | 8/30 | Process Non-System check deletes and cancellations. |
| Fixed Assets Monthly Update | FA | 8/30 | Fixed Asset monthly update process for August, will update September 5th.. |
| Automated closing of PO's | PS | 8/30 | Automated closing of applicable PO's to receiving. |
| Balancing to Available Funds Report | BC | 8/30 | Balancing to Available Funds (BC950) report available in XPTR. |
| CAFR Statements | GL | 8/30 | Agency financial statements due to OSC. |
| Open next period | GL | 8/30 | September (Period 03) is opened. |
| NCAS Saturday Hours | ALL | 8/31 | Production regions up for keying transactions from 7:00 a.m. to 3:00 p.m. with a production cycle update. CLIENT SUPPORT AVAILABLE ONLY FROM 9:00 A.M. TO 2 P.M. |