NCAS
OSC FY '02/03 NCAS APRIL MONTHLY OPERATIONS
CALENDAR FOR PERIOD 10, ENDING 04/30/03
ACTIVITY SYSTEM DATE COMMENTS
Close prior period GL 04/01/03 March 2003 is closed
Pre-Month End Reports GL 04/01/03 Pre-month end reports (MOPRE) available in X/PTR; Current month end reports (MOCUR) discontinued
Health Benefits Interface FC 04/01/03 Health Benefits interface posts first working day of the month.
1099 AP 04/01/03 Verify monthly reports and make any necessary corrections.
Payroll Interface FC 04/03/03 Run Payroll Interface - Cancellation / Rewrite
IT Project Reports GL 04/03/03 IT project reports available in X/PTR
NO PRODUCTION CYCLE ALL 04/04/03 NO PRODUCTION CYCLE UPDATE
Saturday Hours ALL 04/05/03 Production regions up for processing from 9am to 2 pm. No NCAS Help Desk support available.
Inventory Recalculation IN 04/04/03 Inventory recalculation first Friday of every month
Check Reconciliation CR 04/09/03 Check Reconciliation tape is posted tonight
Payroll Interface FC 04/10/03 Run Payroll Interface - Mid-month
IT Project Reports GL 04/10/03 IT project reports available in X/PTR
Certified Reports ALL 04/10/03 Deadline for certifying month end reports. (8th working day)
NO PRODUCTION CYCLE ALL 04/11/03 NO PRODUCTION CYCLE UPDATE
IT Project Reports GL 04/17/03 IT project reports available in X/PTR
HOLIDAY ALL 04/18/03 PRODUCTION REGIONS DOWN FOR THE HOLIDAY
Payroll Interface FC 04/21/03 Run Payroll Interface - Cancellation / Rewrite
Current Month End Reports GL 04/22/03 Current month end reports (MOCUR) available in X/PTR; Pre-month end reports (MOPRE) discontinued
IT Project Reports GL 04/24/03 IT project reports available in X/PTR
Inventory Recalculation IN 04/25/03 Inventory recalculation third Friday of every month (Special time request April Only-Last Friday)
NO PRODUCTION CYCLE ALL 04/25/03 NO PRODUCTION CYCLE UPDATE
Saturday Hours ALL 04/26/03 Production regions up for processing from 9am to 2 pm. No NCAS Help Desk support available.
Payroll Interface FC 04/28/03 Run Payroll Interface - Monthly
Non-System Checks CR 04/30/03 Process Non-System check deletions and cancellations
Inventory FY Central Supply Warehouse IN 04/30/03 Inventory allocation process to be turned off.
Fixed Assets Monthly Update FA 04/30/03 Fixed Asset monthly update process includes depreciation
Open next period GL 04/30/03 May 2003 is opened
Automated closing of PO's MM 04/30/03 Automated closing of applicable PO's to receiving
Balancing to Available Funds Report BC 04/30/03 Balancing to Available Funds (BC950) report available in X/PTR