NCAS

Month-End Report Certification Readiness Checklist

Yes
(N/A)
Completed Task
_____ 1. All unfinished BC documents for the month being certified are completed, approved, and posted.
_____ 2. The suspense distribution (account 99999999899 / center 999999999998) has a zero balance for all companies.
_____ 3. The statewide interface suspense accounts have a zero balance for all companies:
Payroll Interface Suspense - Account 531999 / Center 9999
Health Benefits Suspense - Account 531998 / Center 9999
Mail Service Center Suspense - Account 532849 / Center 9999
_____ 4. Any other agency specific suspense distribution has a zero balance for all companies.
_____ 5. There are no error batches in the Suspended Batch Master (SBM) file with effective dates for the month being certified.
_____ 6. The Disbursing Account (111250) for all companies has a zero balance.
_____ 7. If the month being certified is at the quarter-end, then the quarterly reversion entry has posted with the correct dates and to the correct accounts. For an example, see BD702 and Reversions.
_____ 8. The AP encumbrances and PS encumbrances listed on the Box Totals report (C-GL-BOX TOTALS) are each zero for all companies.
_____ 9. The TOTAL DEBITS equals the TOTAL CREDITS on the Box Totals report (C-GL-BOX TOTALS) for all companies.
_____ 10. The ending cash balances on the Statement of Cash, Receipts, Disbursements, and Balances (BD704) report are correct for all special revenue funds.
_____ 11. All steps in the Report Reconciliation Procedure for General Funds have been completed.
_____ 12. All steps in the Report Reconciliation Procedure for Federal Funds have been completed.
_____ 13. All steps in the Report Reconciliation Procedure for Capital Improvement Funds have been completed.
_____ 14. All steps in the Report Reconciliation Procedure for Special Funds have been completed.
_____ 15. The agency has notified the OSC Support Services Center at 875-4357 that it is ready to pre-certify reports.